Foundation Work
1. Digging (20 partitions): N40,000
2. Concrete Blinding (30 bags): N60,000
3. Mason for Concrete Blinding (2 masons): N20,000
4. Laying of Blocks (480 blocks): N57,600
5. Plinth Beams Formwork (15 partitions): N24,000
6. Casting of Concrete for Plinth Beams (5 bags): N10,000
7. Mason to Dress Plinths: N10,000
8. Filling of the Foundation: N80,000
9. Oversite Concrete (37 bags): N74,000
10. Masons to Dress Oversite Concrete (2 masons): N20,000
Subtotal for Foundation Work: N395,600
Superstructure
1. Laying of Blocks (1,400 blocks): N168,000
2. Lintel Formwork (27 partitions): N43,200
3. Concrete Casting for Lintel (12 bags): N24,000
4. Mason to Dress Lintel: N10,000
5. Blocks Laying for Leveling (3 masons): N30,000
6. Parapet Formwork: N160,000
7. Parapet Concrete Casting (10 bags): N20,000
8. Mason to Dress Parapet: N10,000
9. Roof Carpenter: N100,000
Subtotal for Superstructure: N565,200
Materials Required
1. Blocks (2,400 units): N1,200,000
2. Cement (112 bags): N1,120,000
3. Purlins (170 units): N136,000
4. 2x4 Rafters (1,200 units): N156,000
5. Aluminium (80 square meters): N480,000
6. Sand (8 tippers): N320,000
7. Gravel (4 tippers): N240,000
8. Pegs (2 units): N4,000
9. Mason Rope (3 units): N1,800
10. Laterate (4 tippers): N160,000
11. Rod Y12mm (8 units): N104,000
Subtotal for Materials: N3,921,800
Water Supply (Borehole or Water Tank)
1. Borehole (optional): N300,000 - N1,200,000
or
2. Water Tank (10,000 liters): N150,000 - N250,000
Total Estimated Cost
N395,600 (Foundation Work) + N565,200 (Superstructure) + N3,921,800 (Materials) + N300,000 (Borehole) or N150,000 (Water Tank) = _N5,682,600_ (with borehole) or _N5,032,600_ (with water tank)
The total estimated cost for constructing a 2-bedroom bungalow, including water supply, is approximately _N5,682,600_ (with borehole) or _N5,032,600_ (with water tank).
Avoid parapet to curtail cost
Handle the foundation stage differently to maximize cost too, many spend so much here,some foundation can work very well without some structural expenses👌
Avoid forms and sharps that demand a lot to achieve
Avoid some roofing sheet and if possible go for flat roof
During the finishing maximize and prioritize some space more and not all,yes give all a good touch but in some spaces don’t spend so much on expensive tiles
During the lightening don’t spend much on getting some kind of bulbs because they can cost so much,go for simple bulbs and light up your home.
⚠️NOTE: The estimate made here does not reflect the current prices of Materials and Labor in Nigeria as it changes daily. The estimate also is for the Skeletal Structure (Carcass )of the Building and not for the entire finished work.
However, if you need affordable Land within Imo State, Anambra State, Enugu State, Abia State, Ebonyi State, Porthacourt, Lagos State and Abuja please contact us on the number below.
PHONE: 0808-555-3456